Tehran Province Electricity Distribution Co
Real world bank case study, connection process and tariff base on 2019 sample requests
Row Request Number Aplicant Name Adress Requested power File Number Submit Request date  Contract Settlement date Submit Request and Contract Settlement time External Network Design date External Network Design time  External Network Construction (start date)  External Network Construction (end date) External Network Construction time meter instalation date meter instalation time Total time Branch instalation Cost (RIALS) Project implementation Cost (RIALS)
1 56739086 Reza Fathaliyan Shams Abad Blv, Baharestan, Azadi, Nargis I 150 7407732 2018/8/26 2018/9/9 14 2018/9/24 15 2018/10/26 2018/11/24 30 2018/11/27 3 62 104218000 615000000
2 56733061 Mohammad Ahmadi Sheikh Ahmadlooyi Kahrizak, Qaisar Abad Esmaili ave, kaj, Fourth Door 150 7369009 2018/8/6 2018/8/28 22 2018/9/15 18 2018/9/15 2018/11/6 22 2018/11/12 6 68 203014000 985000000
3 56714112 wahab zamani Shams Abad Blv azadi Narges 3 Second Estate Left 150 7368531 2018/6/12 2018/7/4 22 2018/7/16 12 2018/7/16 2018/8/20 35 2018/8/29 9 78 203014000 750000000